Canadian Zinc: Positive Results from Underground Diamond Drill Program at Prairie Creek Mine
Press Releases
Vancouver, British Columbia, May 5, 2015 – Canadian Zinc Corporation (TSX: CZN;OTCQB: CZICF) (“the Company” or “Canadian Zinc”) is pleased to report that assays have been received for the first four drill holes of the current underground drill program at the Prairie Creek Mine in the Northwest Territories, Canada.
Exploration drilling from the underground drill station #8, in the 870m decline tunnel on section 51000N, is testing for new areas of mineralization in proximity to the mine workings and further detailing Inferred resources with the objective of converting part of the large Inferred Mineral Resource to the Indicated category for potential inclusion in an update of the Preliminary Feasibility Study scheduled to be completed later this year. All of the four holes intercepted the anticipated hosting structures.
In this particular area of the mine, the mineralization occurs either in the Main Quartz Vein (“MQV”), which is a high-grade, steeply dipping, fault structure that hosts the majority of the defined reserves and resources or in the Stockwork Zone (“STK”), which is a series of narrow high-grade veins occurring at an oblique angle to the MQV. All four holes intercepted significant MQV and STK mineralization.
Highlights of Drilling:
- The MQV structure was intersected in all four holes. Hole PCU-15-53 returned the highest grade intercept of 27.5% Pb, 30.5% Zn, 289 g/t Ag over an estimated true width of 3.03 metres.
- Multiple intercepts of STK mineralization were also intersected in all holes in the footwall of the MQV structure, except for PCU-15-54, which had to be abandoned in the MQV prior to penetrating the footwall rocks.
- The best STK intercept occurred in PCU-15-52 which assayed 7.2% Pb, 11.9% Zn, 89 g/t Ag over an estimated true width of 3.63 metres, and with other narrower intercepts withgrades over 20% zinc or lead in three of the four holes.
- The multiple intercepts of STK mineralization occur mostly outside, but adjacent to, the calculated Indicated Resource and this information will add to the STK database and improve resource modelling.
Assay results from the program are as follows:
Drillhole | Mineral | From | To | Core | Est. True | Pb | Zn | Ag | Cu | |||||||||||||
Style | (m) | (m) | Interval(m) | Width(m) | (%) | (%) | (g/t) | (%) | ||||||||||||||
PCU-15-52 | MQV | 105.50 | 107.50 | 2.00 | 1.96 | 14.29 | 6.05 | 203.5 | 0.542 | |||||||||||||
PCU-15-52 | STK | 119.32 | 123.32 | 4.00 | 2.72 | 2.36 | 5.14 | 61.0 | 0.172 | |||||||||||||
PCU-15-52 | STK | 129.24 | 134.60 | 5.36 | 3.63 | 7.17 | 11.93 | 89.2 | 0.163 | |||||||||||||
PCU-15-52 | STK | 135.70 | 137.70 | 2.00 | 1.35 | 5.83 | 16.82 | 51.0 | 0.056 | |||||||||||||
PCU-15-52 | STK | 149.05 | 153.50 | 4.45 | 2.94 | 4.47 | 4.14 | 49.6 | 0.063 | |||||||||||||
PCU-15-52 | STK | 158.22 | 159.72 | 1.50 | 0.98 | 1.03 | 7.99 | 23.2 | 0.074 | |||||||||||||
PCU-15-52 | STK | 161.60 | 162.60 | 1.00 | 0.65 | 7.76 | 21.20 | 67.0 | 0.054 | |||||||||||||
PCU-15-52 | STK | 173.01 | 174.01 | 1.00 | 0.65 | 1.37 | 8.33 | 43.0 | 0.153 | |||||||||||||
PCU-15-52 | STK | 176.80 | 177.88 | 1.08 | 0.71 | 2.54 | 7.22 | 41.0 | 0.094 | |||||||||||||
PCU-15-52 | STK | 191.60 | 192.60 | 1.00 | 0.66 | 0.38 | 3.87 | 18.7 | 0.064 | |||||||||||||
PCU-15-52 | STK | 193.80 | 194.58 | 0.78 | 0.52 | 5.91 | 6.82 | 65.0 | 0.077 | |||||||||||||
PCU-15-52 | STK | 196.00 | 197.00 | 1.00 | 0.67 | 0.78 | 3.71 | 12.2 | 0.023 | |||||||||||||
PCU-15-52 | STK | 206.00 | 207.00 | 1.00 | 0.66 | 0.45 | 6.91 | 8.9 | 0.017 | |||||||||||||
PCU-15-52 | STK | 210.00 | 211.00 | 1.00 | 0.66 | 0.11 | 2.51 | 58.0 | 0.131 | |||||||||||||
PCU-15-52 | STK | 214.48 | 215.48 | 1.00 | 0.66 | 5.01 | 5.57 | 57.0 | 0.072 | |||||||||||||
PCU-15-52 | STK | 220.10 | 221.10 | 1.00 | 0.66 | 9.87 | 23.50 | 115.0 | 0.181 | |||||||||||||
PCU-15-52 | STK | 238.50 | 240.49 | 1.99 | 1.31 | 1.98 | 4.35 | 17.0 | 0.013 | |||||||||||||
PCU-15-53 | Vein | 98.76 | 101.80 | 3.04 | 2.80 | 3.02 | 3.76 | 32.0 | 0.052 | |||||||||||||
PCU-15-53 | MQV | 103.33 | 106.38 | 3.05 | 3.03 | 27.47 | 30.45 | 289.4 | 0.070 | |||||||||||||
PCU-15-53 | STK | 124.66 | 126.60 | 1.94 | 1.42 | 0.32 | 4.11 | 6.5 | 0.012 | |||||||||||||
PCU-15-53 | STK | 130.76 | 132.28 | 1.52 | 1.11 | 8.66 | 5.14 | 76.0 | 0.028 | |||||||||||||
PCU-15-53 | STK | 149.20 | 152.50 | 3.30 | 2.39 | 2.81 | 20.81 | 117.8 | 0.494 | |||||||||||||
PCU-15-53 | STK | 153.62 | 154.67 | 1.05 | 0.76 | 0.54 | 12.10 | 62.0 | 0.297 | |||||||||||||
PCU-15-53 | STK | 161.26 | 162.86 | 1.60 | 1.15 | 0.45 | 16.90 | 41.0 | 0.198 | |||||||||||||
PCU-15-53 | STK | 173.43 | 178.00 | 4.57 | 3.27 | 8.17 | 11.03 | 79.2 | 0.120 | |||||||||||||
PCU-15-53 | STK | 189.00 | 190.00 | 1.00 | 0.71 | 3.71 | 3.05 | 30.0 | 0.038 | |||||||||||||
PCU-15-53 | STK | 193.00 | 194.00 | 1.00 | 0.71 | 2.37 | 5.25 | 25.0 | 0.020 | |||||||||||||
PCU-15-54 | MQV* | 167.34 | 176.70 | 9.36 | 6.63 | 5.95 | 6.87 | 112.0 | 0.328 | |||||||||||||
PCU-15-54 | STK | 181.90 | 182.57 | 0.67 | 0.43 | 3.94 | 7.69 | 84.0 | 0.214 | |||||||||||||
PCU-15-55 | MQV | 121.60 | 123.25 | 1.65 | 1.50 | 8.24 | 2.69 | 61.4 | 0.084 | |||||||||||||
PCU-15-55 | STK | 131.61 | 132.32 | 0.71 | 0.43 | 1.80 | 6.62 | 48.0 | 0.153 | |||||||||||||
PCU-15-55 | STK | 141.95 | 143.02 | 1.07 | 0.66 | 31.00 | 12.00 | 357.0 | 0.403 | |||||||||||||
PCU-15-55 | STK | 144.78 | 146.00 | 1.22 | 0.75 | 2.82 | 6.94 | 83.0 | 0.203 | |||||||||||||
PCU-15-55 | STK | 148.00 | 149.05 | 1.05 | 0.65 | 5.24 | 8.53 | 170.0 | 0.567 | |||||||||||||
PCU-15-55 | STK | 149.92 | 151.07 | 1.15 | 0.71 | 11.50 | 15.40 | 117.0 | 0.148 | |||||||||||||
PCU-15-55 | STK | 154.08 | 155.00 | 0.92 | 0.57 | 1.05 | 9.97 | 15.0 | 0.028 | |||||||||||||
PCU-15-55 | STK | 158.69 | 160.75 | 2.06 | 1.27 | 3.89 | 23.94 | 271.7 | 1.119 | |||||||||||||
* Hole abandoned within the MQV due to technical difficulties. Overall recoveries in PCU-15-54 were approximately 40%. In general, recoveries for all holes averaged approximately 70% from the MQV and 100% for the STK.
Underground Exploration Program
The planned program will comprise about 6,000 metres of diamond drill coring over 21 holes on four, 50-metre sections from three existing diamond drill stations. These initial four holes cover only the upper 300m panel of the mine resource on the 51000N section. The next three deep holes also from this section are awaiting analytical results.
Drilling is presently continuing on the third hole of a proposed ring of six holes on the adjacent 51050N section from underground drill station #9 in the decline tunnel of the 870m Level.
Quality Assurance/Quality Control
The drill core samples were cut by diamond saw and securely, through chain of custody, shipped to AGAT Laboratories for initial multi-element assay by ICP-OES analysis. Further assays and analysis was completed where appropriate standards, duplicates and blanks were inserted and included within the analysis.
Alan Taylor, P. Geo., Chief Operating Officer & Vice President Exploration and a Director of Canadian Zinc Corporation, is responsible for the exploration program, and is a Qualified Person for the purposes of NI 43-101 and has approved this press release.
About the Prairie Creek Mine
The Prairie Creek Mine contains a partially developed infrastructure including an almost complete flotation mill, workshops, accommodations, and support facilities. The Company holds a Type “A” Water Licence which, along with previously issued permits and licences, permits the operation of a mine at Prairie Creek. An update Resource Estimate was recently completed by AMC Mining Consultants (Canada) in March 2015 (refer to March 26, 2015 press release) with overall results as follows:
OVERALL RESOURCE ESTIMATE: MARCH 2015
TOTAL MQV+STK+SMS | TONNES | Zn % | Pb % | Ag g/t |
MEASURED | 1,279,000 | 13.2 | 11.6 | 211 |
INDICATED | 5,309,000 | 9.5 | 9.0 | 131 |
MEASURED & INDICATED | 6,588,000 | 10.2 | 9.5 | 147 |
INFERRED | 7,078,000 | 11.7 | 9.6 | 177 |
The on-going underground diamond drill program is mainly targeting MQV and STK zones with the goal of upgrading part of the Mineral Resource from Inferred to an Indicated classification and in testing for new areas of mineralization in the proximity to the mine workings. The additional Indicated Resources could then be incorporated into a new mine plan to support a longer mine life.
The Company plans to update the 2012 Preliminary Feasibility Study following completion of the current program of underground drilling.
For further information contact:
John F. Kearney
Chairman &
Chief Executive
(416) 362-6686
220 Bay Street,
Suite 1200
Toronto, ON M5J 2W4
Alan B. Taylor
Vice President Exploration
& Chief Operating Officer
(604) 688-2001
Suite 1710 – 650 West Georgia Street,
Vancouver, BC V6B 4N9
Tollfree:1-866-688-2001
Steve Dawson
Vice President
Corporate Development
(416) 203-1418
220 Bay Street,
Suite 1200
Toronto, ON M5J 2W4
E-mail: invest@canadianzinc.com
Website: www.canadianzinc.com
BC2


This article comes from NationTalk:
https://bc.nationtalk.ca
The permalink for this story is:
https://bc.nationtalk.ca/story/canadian-zinc-positive-results-from-underground-diamond-drill-program-at-prairie-creek-mine
Comments are closed.