Taseko Reports Second Quarter 2024 Financial and Operational Performance and Florence Construction Update
July 31, 2024, Vancouver, BC – Taseko Mines Limited (TSX: TKO; NYSE American: TGB; LSE: TKO) (“Taseko” or the “Company”) reports second quarter 2024 Adjusted EBITDA* of $71 million and Earnings from mining operations before depletion and amortization* of $77 million. Second quarter earnings benefited from a $26 million insurance recovery related to mill repairs that were completed in January. Revenues for the second quarter were $138 million. A net loss of $11 million ($0.04 loss per share) was recorded for the quarter and adjusted net income was $31 million ($0.10 per share).
Gibraltar produced 20 million pounds of copper and 185 thousand pounds of molybdenum in the second quarter, as previously disclosed. Production was impacted by planned downtime for the in-pit crusher relocation and other maintenance, and an 18-day mine shutdown for a labour strike. Mill throughput in the quarter was 5.7 million tons, processing an average grade of 0.23% copper. Copper recoveries in the quarter averaged 78%, lower than previous quarters due to interruptions to operating time in both concentrators. Total operating costs (C1)* for the quarter were US$2.99 per pound of copper produced, higher than recent quarters mainly due to lower production levels. The in-pit crusher relocation, a project in development for nearly two years, was completed in the second quarter. Conveyor and electrical tie ins were done by mid-July and the new system is now running at full capacity.
Stuart McDonald, President and CEO of Taseko, commented, “This was our first full quarter with 100% ownership of Gibraltar and despite the operational disruptions, the mine’s financial performance was quite strong as we generated $35 million of operating cashflow. With all of the major project and mill maintenance work now completed at Gibraltar, we’re looking forward to stronger copper production and cashflow generation in the second half.”
Construction activities at the Florence Copper project continued to ramp up in the second quarter and there are over 200 contractors now onsite. Concrete foundations have been poured for the SX/EW plant, tank farms and other key components of the plant site. On the wellfield, 18 production wells were completed to the end of June, in line with the schedule, and development of the pipeline corridor is well advanced. The first evaporation pond, which has been brought ahead in the schedule to provide greater water management flexibility will be fully lined and completed in the next few weeks.
Mr. McDonald added, “We’re pleased with the initial construction progress at Florence as all key activities are advancing on schedule. We’ve also had good success in recruiting key management and technical roles for the commercial operation and now have nearly half of the 170 permanent positions filled. Many of these positions have been filled by local Arizonans and there is excitement about participating in the development of America’s next copper mine. The project remains on schedule for first copper production in the fourth quarter 2025.”
*Non-GAAP performance measure. See end of news release
Second Quarter Review
- Earnings from mining operations before depletion, amortization and non-recurring items* was $76.9 million, Adjusted EBITDA* was $70.8 million, and Adjusted net income* was $30.5 million ($0.10 per share);
- Second quarter cash flow from operations was $34.7 million and net loss was $11.0 million ($0.04 loss per share) for the quarter;
- Gibraltar produced 20.2 million pounds of copper for the quarter. Average head grades were 0.23% and copper recoveries were 78% for the quarter;
- Gibraltar sold 22.6 million pounds of copper in the quarter at an average realized copper price of US$4.49 per pound;
- Total operating costs (C1)* for the quarter were US$2.99 per pound produced;
- On June 1, 2024, operations at the Gibraltar mine were suspended for 18 days due to strike action by its unionized workforce. The mine was put into temporary care and maintenance with only essential staff operating and maintaining critical systems during the strike. Operations at Gibraltar resumed on June 19 after the ratification of a new agreement by union members;
- During the quarter, a total of 5.7 million tons were milled. Throughput was impacted by both the labour strike and planned downtime in Concentrator #1 for the relocation of the primary crusher and maintenance;
- During the quarter, the Company finalized an insurance claim for property damage to Concentrator #2 and business interruption for the associated production impact in 2023 and January 2024. An additional insurance recovery of $26.3 million was recorded in the second quarter, and proceeds are expected to be received in the third quarter;
- Construction of the commercial production facility at Florence is advancing with recent activities focused on wellfield drilling, process pond construction and civil works including pouring of concrete foundations;
- On April 23, 2024, the Company completed an offering of US$500 million aggregate principal amount of 8.25% Senior Secured Notes due May 1, 2030. The majority of the proceeds were used to redeem the outstanding US$400 million 7% Senior Secured Notes due on February 15, 2026. The remaining proceeds, net of transaction costs, call premium and accrued interest, were approximately $110 million and are available to fund capital projects, including construction at Florence Copper; and
- The Company had a cash balance of $199 million at June 30, 2024 and has approximately $308 million of available liquidity including its undrawn US$80 million revolving credit facility.
*Non-GAAP performance measure. See end of news release
Highlights
Operating Data (Gibraltar – 100% basis) | Three months ended June 30, | Six months ended June 30, | ||||
2024 | 2023 | Change | 2024 | 2023 | Change | |
Tons mined (millions) | 18.4 | 23.4 | (5.0) | 41.2 | 47.5 | (6.3) |
Tons milled (millions) | 5.7 | 7.2 | (1.5) | 13.4 | 14.3 | (0.9) |
Production (million pounds Cu) | 20.2 | 28.2 | (8.0) | 49.9 | 53.1 | (3.2) |
Sales (million pounds Cu) | 22.6 | 26.1 | (3.5) | 54.3 | 52.7 | 1.6 |
Scroll right to view more
Financial Data | Three months ended June 30, | Six months ended June 30, | ||||
(Cdn$ in thousands, except for per share amounts) | 2024 | 2023 | Change | 2024 | 2023 | Change |
Revenues | 137,730 | 111,924 | 25,806 | 284,677 | 227,443 | 57,234 |
Cash flows provided by operations | 34,711 | 33,269 | 1,442 | 94,285 | 61,268 | 33,017 |
Net (loss) income (GAAP) | (10,953) | 9,991 | (20,944) | 7,943 | 43,779 | (35,836) |
Per share – basic (“EPS”) | (0.04) | 0.03 | (0.07) | 0.03 | 0.15 | (0.12) |
Earnings from mining operations before depletion, amortization and non-recurring items* | 76,928 | 27,664 | 49,264 | 129,725 | 68,803 | 60,922 |
Adjusted EBITDA* | 70,777 | 22,218 | 48,559 | 120,700 | 58,277 | 62,423 |
Adjusted net income (loss)* | 30,503 | (4,376) | 34,879 | 38,231 | 712 | 37,519 |
Per share – basic (“adjusted EPS”)* | 0.10 | (0.02) | 0.12 | 0.13 | – | 0.13 |
Scroll right to view more
Effective as of March 25, 2024 the Company increased its ownership in Gibraltar from 87.5% to 100%. As a result, the financial results reported in this MD&A include 100% of Gibraltar income and expenses for the period March 25, 2024 to June 30, 2024 (87.5% for the period March 16, 2023 to March 24, 2024, and 75% prior to March 15, 2023). For more information on the Company’s acquisition of Cariboo, please refer to the Financial Statements – Note 3.
The Company finalized the accounting for the acquisition of its initial 50% interest in Cariboo from Sojitz and the related 12.5% interest in Gibraltar in the fourth quarter of 2023. In accordance with the accounting standards for business combinations, the comparable financial statements as of June 30, 2023 and for the three and six months then ended have been revised to reflect the changes in finalizing the consideration paid and the allocation of the purchase price to the assets and liabilities acquired.
*Non-GAAP performance measure. See end of news release
Review of Operations
NT4


This article comes from NationTalk:
https://bc.nationtalk.ca
The permalink for this story is:
https://bc.nationtalk.ca/story/taseko-reports-second-quarter-2024-financial-and-operational-performance-and-florence-construction-update
Comments are closed.